Real options: the value of flexibility
The lessons "Net present value and internal rate of return" and "Discounted cash flow valuation" valued a project as if its plan were fixed today. Real managers can wait, expand, scale down or stop as information arrives. This lesson values that flexibility with the binomial tree from "Multi-step trees and backward induction" and the early-exercise logic from "American options and early exercise".
Flexibility in investment decisions
The static NPV rule compares the present value of a project's cash flows with the investment and accepts when . It treats the decision as now or never: invest today on the current plan, or drop the project for good. Most real projects are not like that. A firm holding a licence or a plot of land can usually delay the investment, expand capacity if demand turns out strong, abandon the project and sell the assets if it goes badly, or switch inputs or outputs. Each of these is a right without an obligation, so each has the payoff shape of an option. Such options on real assets are called real options.
Mapping a project to an option
Take the right to invest in a project. Exercising it means paying and receiving a project worth , so the payoff is , the payoff of a call. The pieces translate as follows:
- Underlying: the present value of the project's cash flows, the quantity a DCF valuation produces.
- Strike: the investment cost .
- Maturity : how long the opportunity stays open (a licence period, a patent life, a lease on land).
- Volatility : the uncertainty of , how much the project's value can change per year.
- Dividend yield : the cash flows the project would already pay while the firm is waiting, as a yield on . They are lost by waiting.
Since the firm can invest at any date up to , the option to delay is an American call on with strike .
When waiting pays
With the argument from "American options and early exercise" carries over. Investing at time gives , while keeping the right is worth at least , which is larger: waiting delays the payment of and keeps the protection against a fall in . So with no forgone cash flows it is never optimal to invest before .
With waiting has a cost. A project already running pays roughly per year, and a firm that waits receives none of it. When the project is deep in the money, a fall below is unlikely, so the protection is worth little, while the forgone cash flow is large because is large. Then investing at once beats waiting, exactly as a large dividend can make early exercise of an American call optimal.
Valuation on a binomial tree
Split into steps of length . As in "Multi-step trees and backward induction", moves up by or down by in each step. The forgone cash flows lower the risk-neutral growth of from to , so the risk-neutral probability is
At maturity the value of the opportunity is . At every earlier node the firm compares investing now with waiting one more step, and backward induction keeps the better of the two:
The value at the root is the value of the investment opportunity, called the expanded NPV. A now-or-never decision is worth , since a project with negative NPV is simply rejected. The difference is the value of flexibility.
Expanded NPV = now-or-never value + value of flexibility, where the now-or-never value is . Some texts write expanded NPV = static NPV + option premium; with a negative static NPV the premium then also covers the shortfall below zero.
Worked example
Let , , , , and years, with one step per year (). Then , , the one-step discount factor is , and
The static NPV is , so the now-or-never rule rejects the project. The tree tells a different story.
- Year 3: is 245.96, 134.99, 74.08 or 40.66. The opportunity is worth : 140.96, 29.99, 0 and 0.
- Year 2, : waiting is worth , investing gives 77.21. Invest. The forgone cash flow in the last year, about , exceeds the interest saved on , about 5.12.
- Year 2, : waiting 12.61 against now, so wait. At the opportunity is worthless.
- Year 1, : waiting against 29.99 now, so wait. At : waiting 5.30, wait.
- Year 0: waiting against now, so wait.
The expanded NPV is 19.28. A project that the static rule rejects is a valuable opportunity, provided the firm keeps the right to wait. All of its 19.28 is value of flexibility.
The figure uses the same setting: , and a 3-step tree over years. Sliders set the investment cost (60 to 140), the volatility (10% to 60%) and the forgone cash-flow yield (0% to 10%). The chart plots the static NPV and the expanded NPV against from 60 to 140, with a vertical line at the chosen . The readouts show the static NPV, the expanded NPV, the value of flexibility (expanded NPV minus ) and today's decision. Set and note that the expanded NPV stays above the static NPV for every , so waiting always has value. Raise and lower to find the region where investing now is optimal. Raise and watch the expanded NPV curve lift away from the static line.
- Static NPV
- -5.00
- Expanded NPV
- 19.28
- Value of flexibility
- 19.28
- Today's decision
- Wait
The option to expand
Suppose that by paying an extra the firm can scale the project up by a fraction , turning into . At a date when the option can be used, the project with the option is worth . The expansion right is therefore a call on with strike , valued on the same tree by adding this term at the decision nodes. It pays off exactly in the states where demand turned out strong.
The option to abandon
If the firm can stop the project and sell its assets for a salvage value , then at each decision date the project is worth . The abandonment right is a put on with strike . It limits the downside: in bad states the firm walks away with instead of keeping a project worth less. On the tree, each node takes the larger of the continuation value and .
Limits of the analogy
Option pricing rests on replication: the option's payoff can be copied by trading the underlying, which pins the price down. A project's value is not traded, so no such portfolio exists in general. The risk-neutral valuation used above is then an approximation, justified if some traded asset (a commodity, a listed firm in the same business) moves closely with . The inputs are also harder to estimate than for a stock option: and have to be inferred from forecasts, and competitors may take the opportunity away before .
Summary
- Static NPV assumes a now-or-never decision; the rights to delay, expand, abandon or switch are options on the project value .
- The option to delay is an American call on with strike ; the forgone cash-flow yield plays the role of a dividend yield.
- With investing early is never optimal; with investing at once can be optimal when the project is deep in the money.
- On a binomial tree with , each node takes the maximum of investing now and waiting; the root value is the expanded NPV.
- Expanding is a call and abandoning is a put on ; since is not traded, the valuation is an approximation.